Massachusetts
Highway Sign Replacement Contract List through 2028
Current Projects as of July 11, 2025
Route
Where
Percent Complete
Completion Date
Attleboro to Norwood
100%
Autumn
2021*
[Installation of all overhead signs not complete**]
Worcester to Leominster
100%
Autumn 2024*
[Work completed-2/1/25]1
Dartmouth to Wareham 27%
Autumn 2025
[Overhead sign foundation work continues-7/2/25]
Wareham to Raynham
42%
Summer 2026 [Overhead sign support and sign
panels being installed-7/8/25]
Braintree to Plymouth
3%
Spring 2026
[Work started on installing ground mounted signage-6/24/25]
Peabody to Gloucester
52%
Autumn 2025
[Work continues- 7/8/25]
Freetown to Taunton
0%
Autumn 2026
[Notice to Proceed-7/2/25]
Uxbridge to Worcester
0%
2027
[Notice to Proceed-4/9/25]
*Project continues (will continue) after original estimated date of
completion, MassDOT Project listings no longer include a projected
completion date as of July 2021.
**Despite MassDOT listing as project complete, two 1/2 mile advance
signs for the I-495 exit have not been installed as of 8/16/24.
1. ProjectInfo
site states completion, will confirm in future road trip.
2. Work
completed, photos of installed signs available at my Misc.
Mass. Road Signs Gallery:
Future Projects
Route
Where
To be Let in (or FY*)
/
Central Artery/Tunnel
System Spring 2026
Lexington to Reading
2026
[75% Package Received- 6/8/25]
Springfield to Chicopee
Summer 2026 (was Spring 2026)
Auburn to Webster
Spring 2027
Harvard
to Concord
Spring 2026 (Was Summer 2025)
Templeton
to Lancaster
2028
West
Springfield to Agawam Spring 2027
Methuen
Winter 2025/2026
[75% Package Received- 3/26/25]
*For those having no date official date for start of construction.
Notes:
Information current as of July 11, 2025 obtained from MassDOT Project
Listings (ProjectInfo) for Structural Signing contracts under construction or design, downloaded from:
https://www.mass.gov/service-details/massdot-project-info
For sign projects
planned between 2016 and 2020, MassDOT had contractors install exit tabs and gore signs that can fit future milepost
based numbers. MassDOT then renumbered these exits to the milepost system under 3 contracts from
October 2020 to August 2021.