Massachusetts
Highway Sign Replacement Contract List through 2027
Current Projects
as of March 19, 2024
Route
Where
Percent Complete
Completion Date
Attleboro to Norwood
100%
Fall
2021*
[Installation of all overhead signs not complete**]
Worcester to Leominster
30%
Autumn
2024
[Work continues-3/1/24]
Attleborough to N. Attleborough 50%
Spring 2024
[Overhead signs
being installed-2/17/24]
Chelsea to
Danvers
89%
Autumn 2021*
[Overhead signs installation continues-2/3/24]
Burlington to
Tyngsborough 54%
Spring 2023*
[Overhead sign installation has
begun-2/8/24]
Wareham to
Bourne
?%
Spring 2024
[Contractor to place ground level signs-3/7/24]
*Project continues (will continue) after original estimated date of
completion, MassDOT Project listings no longer include a completion date
as of July 2021.
**Despite MassDOT listing as project complete, two 1/2 mile advance
signs for the I-495 exit have not been installed as of 3/12/23 as well as
a new sign for the I-495 exit on I-95 South that was knocked down soon
after installation.
Future Projects
Route
Where
To be Let in
/
Central Artery/Tunnel
System Spring 2026
Dartmouth to
Wareham
Summer 2024 [Project Advertised, 3/16/24,
Winning bid to be announced 4/30/24]
Springfield to Chicopee
Spring 2026 (was Summer 2025)
Auburn to
Webster
2027*
Wareham to Raynham
Summer 2024 [PS&E Received, 1/16/2024]
Harvard
to Concord
Spring 2026 (Was Summer 2025)
Braintree to Plymouth
Spring 2025 [75% Design
package received as of 12/18/23]
West
Springfield to Agawam
2027*
Peabody to Gloucester
Summer 2024 [Project Advertised, 3/16/24,
Winning bid to be announced 4/30/24]
Freetown to Taunton
Summer 2025 (Was Spring
2025)
Uxbridge to Worcester
Spring 2025 [25% Design Package Received, 12/8/23]
*New MassDOT Project listing containing no date for start of
construction, assuming 2027 since only projects up through FY 2026 have
years listed.
Notes:
Information current as of March 19, 2024 obtained from MassDOT Project
Listings (ProjectInfo) for Structural Signing contracts under
construction or design, downloaded from:
https://www.mass.gov/service-details/massdot-project-info
For sign projects
planned between 2016 and 2020, MassDOT had contractors install exit tabs
and gore signs that can fit future milepost based numbers. MassDOT then
renumbered these exits to the milepost system under 3 contracts from
October 2020 to August 2021.